Question No: 51 – (Topic 1)

Which of the following areas is addressed in the Project Charter?

  1. Project team members

  2. Work Breakdown Structure (WBS)

  3. Business needs

  4. Communications venue

Answer: C

Question No: 52 – (Topic 1)

A project baseline should be captured when the:

  1. project manager is satisfied with the project tasks and risks associated.

  2. sponsor is ready for work to begin and conducts a kick-off meeting.

  3. schedule is fully developed with activity names, durations, dependencies, and costs.

  4. WBS and WBS dictionary have been defined and agreed upon.

Answer: C

Question No: 53 – (Topic 1)

Which of the following shows how often contracts would be closed for the procurements on a project?

  1. During phase gate review

  2. After the project is completed

  3. At the end of the project

  4. At the end of the contract

    Answer: D

    Question No: 54 – (Topic 1)

    Given the following:

    1. Senior management support will maintain throughout the duration of the project.

    2. Technical hardware onsite is sufficient to support the new application.

    3. Network connectivity is able to support the new product.

    4. All scope changes will follow the change control process.

      Which of the following components of a scope document would BEST capture the above criteria?

      1. Assumptions

      2. Constraints

      3. Key performance indicators

      4. Objectives

Answer: A

Question No: 55 – (Topic 1)

It is the first week after a project kick-off. The project team is not making much progress on decisions needed and are disagreeing with each other. Which of the following represents the team#39;s current stage?

  1. Storming

  2. Norming

  3. Forming

  4. Performing

Answer: A

Question No: 56 – (Topic 1)

A stakeholder wants to add another requirement to the deliverable. Which of the following will the project manager do to determine the change’s effect on the project?

  1. Performing an impact analysis

  2. Identifying a change

  3. Coordinating with stakeholders to select the course of action

  4. Filling out a change control

Answer: A

Question No: 57 – (Topic 1)

Which of the following describes the total amount of money approved for spending on a project?

  1. VAC

  2. BAC

  3. ETC

  4. EAC

Answer: B

Question No: 58 – (Topic 1)

Which of the following is a component of a performance evaluation for an individual?

  1. Resource utilization

  2. Role assessment

  3. Scope management

  4. Variance management

Answer: B

Question No: 59 – (Topic 1)

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the following?

  1. Cost performance index

  2. Risk mitigation

  3. Schedule variance

  4. Cost variance

Answer: C

Question No: 60 – (Topic 1)

A well-written scope document will include which of the following? (Select TWO).

  1. Contact information

  2. Milestones

  3. Stakeholders

  4. Constraints

  5. Project acceptance criteria

  6. Project tasks

Answer: D,E

100% Dumps4cert Free Download!
Download Free Demo:PK0-003 Demo PDF
100% Dumps4cert Pass Guaranteed!
Download 2018 Dumps4cert PK0-003 Full Exam PDF and VCE

Dumps4cert ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No