Question No: 171 – (Topic 2)

Which of the following describes a WBS?

  1. A schedule-oriented decomposition of the project work

  2. A deliverable-oriented decomposition of the project work

  3. An action-oriented decomposition of the project work

  4. An owner-oriented decomposition of the project work

Answer: B

Question No: 172 – (Topic 2)

A project manager wants to ensure the project maintains funding and satisfies the intent of the project. Which of the following functions within the communication plan can reduce scope creep?

  1. Implementing change requests

  2. Periodically updating stakeholder

  3. Updating risk register with changes

  4. Analyzing performance information

Answer: B

Question No: 173 – (Topic 2)

Which of the following is the status of an active project with an SPI of 1.1 and a CPI of .9?

  1. Behind schedule, and over budget

  2. Ahead of schedule, and under budget

  3. Behind schedule, and under budget

  4. Ahead of schedule, and over budget

Answer: D

Question No: 174 – (Topic 2)

A project timeline is at risk of not meeting the completion time for developing a smart phone application. In order to meet the date, the code can be pushed out to the testers while getting scanned by the code security software. Development time will be shorter, but there could be a security risk to the application. Which of the following techniques does this describe?

  1. Crashing

  2. Avoidance

  3. Optimizing

  4. Fast-tracking

Answer: D

Question No: 175 – (Topic 2)

Which of the following is the main purpose of a work breakdown structure?

  1. To decompose the list of deliverables

  2. To identify key stakeholders and their influence

  3. To assign resources to activities

  4. To determine total project duration

Answer: A

Question No: 176 – (Topic 2)

A project manager wants to ensure that end users receive proper training prior to implementation. In which of the following documents should the project manager outline the necessary training?

  1. Work breakdown structure

  2. Transition plan

  3. Communication plan

  4. Lessons learned

Answer: B

Question No: 177 – (Topic 2)

Which of the following tools should be used to analyze quality issues? (Select TWO).

  1. Risk register

  2. Pareto chart

  3. Histogram

  4. SWOT analysis

  5. RACI chart

Answer: B,C

Question No: 178 – (Topic 2)

Which of the following tools will assist in providing a clear assessment of risks specific to the project?

  1. Risk matrix

  2. Risk register

  3. Risk profile

  4. Risk management plan

Answer: A

Question No: 179 – (Topic 2)

A key stakeholder asks the project manager to change the color of the envelope that will be used as part of the project deliverable. This is a minor change that will require the project manager to do which of the following FIRST?

  1. Enter the change in the change log.

  2. Provide a budget estimate.

  3. Implement the change.

  4. Analyze the impact of the change.

Answer: A

Question No: 180 – (Topic 2)

The change control board has been unable to come to a consensus regarding if a change that affects the charter should be approved. Which of the following roles has the authority to authorize changes to the charter?

  1. Project sponsor

  2. Senior managers

  3. Project manager

  4. Stakeholders

Answer: A

100% Dumps4cert Free Download!
Download Free Demo:PK0-003 Demo PDF
100% Dumps4cert Pass Guaranteed!
Download 2018 Dumps4cert PK0-003 Full Exam PDF and VCE

Dumps4cert ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No