Ensurepass.com : Ensure you pass the IT Exams
2018 May Microsoft Official New Released 70-498
100% Free Download! 100% Pass Guaranteed!

Delivering Continuous Value with Visual Studio 2012 Application Lifecycle Management

Question No: 61

You are developing release plans for a new software development project. You need to document a flexibility matrix.

Which three elements should you use? (Each correct answer presents part of the solution. Choose three.)

  1. schedule

  2. risk mitigation

  3. scope

  4. cost or resources

  5. decision-making authority

  6. solution architecture

Answer: A,C,D

Question No: 62

Your client is utilizing the Microsoft Visual Studio Scrum 2.0 process template.

Your client provides a set of acceptance tests for Product Backlog Items (PBI). The PBI work has been committed to in the upcoming sprint.

You need to ensure that the status of the acceptance tests can be reported from TFS. What should you do?

  1. Store the acceptance test as rows in a Microsoft Excel spreadsheet and attach the spreadsheet to the PBI work item.

  2. Store the acceptance test as rows in a Microsoft Excel spreadsheet. Save the spreadsheet in the associated project portal site and link it to the PBI work items.

  3. Create Test case work items. Link the test cases to the PBI work items by using a Tests link type.

  4. Create Test case work items. Link the PBI work items by using a Parent link type to the test cases.

Answer: C

Question No: 63

You manage a development team that uses the Microsoft Visual Studio Scrum 2.0 process template.

You establish a product backlog, allocate backlog items for a sprint, and define the tasks required to complete the sprint.

You need to ensure that the agreed upon work is assigned to team members. Who should be responsible for assigning work to team members?

  1. Team members

  2. Product owner

  3. Scrum master

  4. Team lead

Answer: A

Question No: 64 DRAG DROP

Your IT department uses a custom SharePoint list to capture help desk calls and ticket information. Management asks you to report the mean time to repair (MTTR) on a weekly basis.

You need to modify the list to capture the data necessary to prepare the report.

What should you do? (To answer, move the four appropriate actions from the list of actions to the answer area and arrange them in the correct order.)

Ensurepass 2018 PDF and VCE

Answer:

Ensurepass 2018 PDF and VCE

Explanation:

Box 1:

Ensurepass 2018 PDF and VCE

Box 2:

Ensurepass 2018 PDF and VCE

Box 3:

Ensurepass 2018 PDF and VCE

Box 4:

Ensurepass 2018 PDF and VCE

Note: Mean time to repair (MTTR) is a basic measure of the maintainability of repairable items. It represents the average time required to repair a failed component or device.

Expressed mathematically, it is the total corrective maintenance time divided by the total number of corrective maintenance actions during a given period of time. It generally does not include lead time for parts not readily available, or other Administrative or Logistic Downtime (ALDT).

Question No: 65

You are utilizing the Microsoft Solution Framework (MSF) for Agile Software Development

6.0 process template.

You need to track progress for the current sprint.

Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)

  1. Review team capacity.

  2. From the Product Backlog view of the current sprint, review the By Work capacity bars for each contributor.

  3. Review the task board.

  4. Review the burndown chart.

  5. From the project portal, review the Iteration Backlog spreadsheet.

Answer: A,D,E

Question No: 66

Historically your IT group has done a poor job of reporting issues and successes to key decision makers in a timely manner, due to incomplete or inconsistent application lifecycle management (ALM) practices.

You are implementing Scrum as the process framework for new projects. The scrum master will publish daily progress reports to the product owner and key stakeholders.

You need to view daily progress and identify if bottlenecks are occurring in the development process.

Which report should you use?

  1. Bug Trends

  2. Sprint Burndown

  3. Cumulative Flow

  4. Release Burndown

    Answer: C

    Question No: 67 DRAG DROP

    You are developing a new application that contains complicated validation and transformation logic on data pulled from three separate source systems.

    You need to get feedback from your stakeholders to verify that your application meets their requirements before any other development tasks have been started. You also need to ensure that this application sub-system is correct before any other dependent module can be developed.

    What should you do? (To answer, move the five appropriate actions from the list of actions to the answer area and arrange them in the correct order.)

    Ensurepass 2018 PDF and VCE

    Answer:

    Ensurepass 2018 PDF and VCE

    Question No: 68

    You develop an n-tier application that includes the following components:

    ->Database

    ->Data access layer

    ->Business logic layer

    ->Presentation layer (website)

    The database has approximately 100 tables and stores large amounts of data. You need to select a unit testing strategy to verify the business logic layer.

    What should you do?

    A.

  • Create a mock data access layer.

  • Configure the business logic layer to use the mock data access layer.

  • Write tests against the business logic layer.

    B.

  • Create a mock data access layer.

  • Write tests against the mock data access layer.

    C.

  • Create a mock business logic layer and a test database.

  • Configure the data access layer to target the test database.

  • Write tests against the business logic layer.

    D.

  • Create a test database from a backup of the live database.

  • Configure the data access layer to target the test database.

  • Write tests against the data access layer.

  • Answer: A

    Question No: 69 DRAG DROP

    Your team uses Microsoft Visual Studio Team Foundation Server (TFS) to manage the software development process. You are using the Microsoft Visual Studio Scrum process template on your TFS Team Project.

    Your product owner adds new product backlog items to your backlog.

    You need to estimate how many sprints are necessary to complete the work in your backlog.

    You have set a value for the Effort field for each product backlog item found in your backlog as a first step.

    Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

    Ensurepass 2018 PDF and VCE

    Answer:

    Ensurepass 2018 PDF and VCE

    Explanation:

    Box 1:

    Ensurepass 2018 PDF and VCE

    Box 2:

    Ensurepass 2018 PDF and VCE

    Box 3:

    Ensurepass 2018 PDF and VCE

    Once you’ve completed a sprint or two, you can use the velocity chart to forecast how much of your backlog you’ll finish each sprint.

    Forecast your upcoming sprint

      1. From the backlog page, open the velocity chart.

        In the chart, you can see how many story points (or whatever you use to estimate your backlog) your team has completed in the previous sprints.

      2. Go back to the backlog page, turn forecasting on, and enter your predicted velocity.

        Ensurepass 2018 PDF and VCE

        Changing velocity changes forecast lines

        Forecast lines show how much work your team should be able to complete in future sprints.

        Question No: 70

        Your team uses Microsoft Visual Studio Team Foundation Server (TFS) to manage the software development process. You use the Microsoft Visual Studio Scrum 2013 process template on your TFS Team Project.

        You work with the product owner to define and prioritize the Product Backlog.

        Due to new business regulations, a group of product backlog items need to be implemented sooner than initially planned.

        You need to raise the business value of the affected product backlog items.

        Which two actions should you perform? Each correct answer presents a complete solution.

        1. Edit the Product Backlog Item work item by changing the resolution to a higher value.

        2. Select the Product Backlog Item, and drag it towards the top of the backlog.

        3. Adjust the business value on the Product Backlog Item.

        4. Edit the Product Backlog Item work item by changing the priority to a higher value.

        5. Select the Product Backlog Item, and drag it towards the bottom of the backlog.

    Answer: B,C

    100% Ensurepass Free Download!
    Download Free Demo:70-498 Demo PDF
    100% Ensurepass Free Guaranteed!
    70-498 Dumps

    EnsurePass ExamCollection Testking
    Lowest Price Guarantee Yes No No
    Up-to-Dated Yes No No
    Real Questions Yes No No
    Explanation Yes No No
    PDF VCE Yes No No
    Free VCE Simulator Yes No No
    Instant Download Yes No No