Question No: 131 – (Topic 2)

A supplier is not required on a .

  1. Invoice

  2. Receipt

  3. Quotation

  4. Requisition

  5. Purchase Order

  6. Request For Quotation

Answer: D

Question No: 132 – (Topic 2)

ACME requires cycle counting variance approval tolerances and the Approval Required option is set to: If out of tolerance. When the actual count falls within tolerance, Inventory

.

  1. automatically approves and posts the cycle count adjustment

  2. automatically approves, but does not post the cycle count adjustment

  3. holds the cycle count adjustment for approval and posts it after approval

  4. holds the cycle count adjustment for a recount and does not post the adjustment

Answer: A

Question No: 133 – (Topic 2)

Identify two situations in which item information on a requisition CANNOT be sourced from the Approved Supplier List. (Choose two).

  1. The supplier status is New.

  2. The Approved Supplier List is disabled at the line level.

  3. The Use Approved Supplier flag is unchecked for the item.

  4. The supplier is active but the supplier site is made temporarily inactive.

  5. The supplier status is set to Debarred, but the business rule Sourcing is set to Allow.

Answer: B,C

Question No: 134 – (Topic 2)

A multinational company operates in three countries, with one operating unit (OU) in each. Each OU is linked to one inventory organization. One of the inventory organizations is a manufacturing plant. Which two statements are correct? (Choose two).

  1. A location is a legal address, it cannot be a Ship-To site for more than one country.

  2. A location is unique to a specific OU responsibility when the Global check box is selected.

  3. When a location is flagged as local, you must assign the local inventory organization to it.

  4. The Ship-To location and Ship-To site for the same inventory location can be in different countries.

  5. You cannot set a default receiving location in the Receiving Options for each inventory organization.

Answer: D,E

Question No: 135 – (Topic 2)

Which three statements are true regarding Inventory replenishment methods? (Choose three.)

  1. Min-max planning considers order cost.

  2. Min-max planning considers carrying cost.

  3. Reorder point planning considers order cost.

  4. Reorder point planning considers replenishment lead time.

  5. Min-max planning can be performed at the subinventory level.

  6. When an item is defined, both reorder point planning and min-max planning can be specified to place limits on the calculated reorder point.

Answer: C,D,E

Question No: 136 – (Topic 2)

The on-hand quantity balance for item A is 100 and item B is 200. A shipment of 50 for item A and 50 for item B arrived today. The receiving clerk created a receipt for the shipment.

After the receipt, the on-hand quantity of items A and B are 150 and 200 respectively. Which one of the possible receipt routing options for items A and B is correct?

  1. Item A = Direct Delivery; Item B = Standard Receipt

  2. Item A = Standard Receipt; Item B = Direct Delivery

  3. Item A = Inspection Required; Item B = Direct Delivery

  4. Item A = Inspection Required; Item B = Standard Receipt

  5. Item A = Standard Receipt; Item B = Inspection Required

Answer: A

Question No: 137 – (Topic 2)

A parts distributor has a facility that includes several buildings that are used as warehouses. All the warehouses together represent one subinventory in an inventory organization. Each building is multistoried, and each floor (story) has several rooms within each building that are unique to that building. All rooms are used to store material, and the distributor needs the ability to store material and pick material from these rooms. What is the optimum number of segments that you would recommend for the Stock Locator flexfield?

  1. 1

  2. 2

  3. 3

  4. 4

  5. 5

Answer: C

Question No: 138 – (Topic 2)

Which three statements are true about the Move Order process? (Choose three.)

  1. Requisition and pick release orders are preapproved.

  2. Replenishment and pick wave move orders are preapproved.

  3. Requisition and pick release orders are preapproved and require inspection.

  4. If no planner is specified for the item, the requisition line is automatically approved.

  5. If no approvals are required in your organization, set the inventory organization parameters Timeout Period to 0 and the Timeout Action to Approve Automatically.

Answer: B,D,E

Question No: 139 – (Topic 2)

You want Oracle Inventory to automatically create move orders while performing min-max planning. To enable that functionality, you would need to define the .

  1. subinventory supply source type at the pull level

  2. Move Order Timeout Action to a value greater than zero

  3. Move Order Timeout Period to a value greater than zero

  4. subinventory supply source type at the subinventory or item level

Answer: D

Question No: 140 – (Topic 2)

Your customer is planning to close the accounting period in Inventory. Before closing the period, the customer would like to view the total number of pending transactions in one form. Which form would provide this information?

  1. Pending Status

  2. View Material Transactions

  3. Find Pending Transactions

  4. Transaction Open Interface

  5. Inventory Accounting Period

Answer: E

100% Free Download!
Download Free Demo:1z0-520 Demo PDF
100% Pass Guaranteed!
Download 2018 EnsurePass 1z0-520 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2018 EnsurePass IT Certification PDF and VCE