Managing Projects and Portfolios with Microsoft PPM

Question No: 1 HOTSPOT

You are evaluating the requirements for creating a new portfolio analysis.

For each of the following statements, select Yes if the statement is true. Otherwise, select No.

Dumps4Cert 2018 PDF and VCE

Answer:

Dumps4Cert 2018 PDF and VCE

Question No: 2 DRAG DROP

You are the administrator for an organization that uses Microsoft PPM. Users must be able to create projects by using predefined templates.

You need to create a new Enterprise Project Template and make it available for users.

Dumps4Cert 2018 PDF and VCE

Answer:

Dumps4Cert 2018 PDF and VCE

Question No: 3

A company is using Microsoft PPM to track task progress, The company implements standard overtime and non-billable time tracking.

You observe that you cannot enter overtime hours in your current timesheet. You need to ensure that you can enter overtime hours. What should you do?

  1. In your timesheet add Overtime, and then enter the overtime hours,

  2. In your timesheet switch to the My Work view, and then enter the overtime hours.

  3. In your timesheet add Non-Billable, and then enter the overtime hours.

  4. Ask your project administrator to increase Maximum Hours per Day.

  5. In your timesheet add the overtime hours to your regular hours.

Answer: A

Question No: 4

Your company has had several large projects fail due to cost overruns and the lack of available resources. These projects use an enterprise project type named Large IT Project and use a workflow to govern the approval of the projects. The workflow consists of four phases; Initiate, Plan, Execute, and Close.

You need to use Microsoft PPM to compare the value that a new project provides with the cost of implementing the project.

Which three configuration changes should you make? Each correct answer presents part of the solution.

  1. Navigate to PWA Settings Edit the Large IT Project project type, and in the Available Project Detail Page section, add the Strategic Impact form.

  2. Create a project-level custom field that will be used to enter the total cost of a project

  3. Define your company#39;s strategic drivers, and enter them into the Strategic Impact form.

  4. Create a project-level custom field that will be used to enter the value statements of why this project should be undertaken.

  5. Define your company#39;s strategic drivers and enter them into the driver library.

  6. In PWA Settings, edit and then save the stage information. In the Available Project Detail Page section, add the Strategic Impact.

Answer: B,C,E

Question No: 5 HOTSPOT

Your organization uses Microsoft PPM for tracking projects.

For one specific cross-functional project different managers are responsible for different phases. These managers must be able to receive the task status updates for the project tasks that they are responsible for.

For each of the following statements, select Yes if the statement is true. Otherwise, select No.

Dumps4Cert 2018 PDF and VCE

Answer:

Dumps4Cert 2018 PDF and VCE

Question No: 6

The SharePoint Farm administrator for a company installs Microsoft PPM and grants you administrative rights for PWA. The PWA instance is accessible at the URL: https://AppServer/Live.

You determine that the client needs to implement a Resource Breakdown Structure (RBS) to provide access to projects.

You need to ensure that the RBS is implemented. What should you do first?

  1. Run the Set-SPPRojectPermissionMode Windows PowerShell cmdlet.

  2. Ask the SharePoint administrator to run the Sct-SPPRojectPcrmissionMode Windows PowerShell cmdlet.

  3. From Settings, select Manage Groups.

  4. From Site Settings, activate the Project Web App Connectivity feature.

Answer: A

Question No: 7 HOTSPOT

You are the project manager for a real estate management company. You are using Microsoft Project to manage the development of a new restaurant The schedule includes a task named Equipment delivery.

Your supplier states that they will start delivering stoves, refrigerators, and other equipment on June 9, 2016.

You need to modify the Equipment delivery task.

How should you configure the constraint for the task? To answer, select the appropriate option from each list in the answer area.

Dumps4Cert 2018 PDF and VCE

Dumps4Cert 2018 PDF and VCE

Answer:

Dumps4Cert 2018 PDF and VCE

Question No: 8

You use Microsoft PPM to manage an e-commerce portal development program.

The program is separated into individual projects that represent each area of development. This allows each group to manage its own tasks while still having progress visibility at the program level.

You need to be able to see all programs and their associated individual projects from within Project Center.

What should you do?

  1. Select the Enterprise Project Type Name field as the value for grouping.

  2. Select the Master Program field as the value for filtering.

  3. Select the Subprojects check box.

  4. Select the Project Details view.

Answer: C

Question No: 9 HOTSPOT

A project that you manage begins to go over budget

You need to reduce the scope of the project and retain a baseline record for all tasks.

For each of the following statements, select Yes if the statement is true. Otherwise, select No.

Dumps4Cert 2018 PDF and VCE

Answer:

Dumps4Cert 2018 PDF and VCE

Question No: 10

This question requires that you evaluate the underlined text to determine if It is correct. Cost resources affect the schedule when they#39;re assigned to tasks.

Review the underlined text. If it makes the statement correct select quot;No change is needed.- If the statement is incorrect, select the answer choice that makes the statement correct

  1. No change is needed.

  2. Work resources

  3. Material resources

  4. Budget work resources

Answer: C

100% Dumps4cert Free Download!
Download Free Demo:70-348 Demo PDF
100% Dumps4cert Pass Guaranteed!
70-348 Dumps

Dumps4cert ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No