QUESTION 71

You are the project manager of the GHG project. You are preparing for the quantitative risk analysis process. You are using organizational process assets to help you complete the quantitative risk analysis process. Which one ofthe following isNOTa valid reason to utilize organizational process assets as a part of the quantitative risk analysis process?

 

A.

You will use organizational process assets for risk databases that may be available from industry sources.

B.

You will use organizational process assets for studies of similar projects by risk specialists.

C.

You will use organizational process assets to determine costs of all risks events within thecurrent project.

D.

You will use organizational process assets for information from prior similar projects.

 

Correct Answer: C

 

 

QUESTION 72

Which of the following objectives are defined by integrity in the C.I.A triad of information security systems? Each correct answer represents a part of the solution. Choose three.

 

A.

It preservesthe internal and external consistency of information.

B.

It prevents the unauthorized or unintentional modification of information by the authorized users.

C.

It prevents the modification of information by the unauthorized users.

D.

It prevents the intentional or unintentional unauthorized disclosure of a message’s contents .

 

Correct Answer: ABC

 

 

QUESTION 73

You and your project team are just starting the risk identification activities for a project that is scheduled to last for 18 months. Your project team has already identified a long list of risks that need to be analyzed. How often should you and the project team do risk identification?

 

A.

At least once per month

B.

Identify risks is an iterative process.

C.

It depends on how many risks are initially identified.

D.

Several times until the project moves into execution

 

Correct Answer: B

 

 

QUESTION 74

Eric is the project manager of the MTC project for his company. In this project a vendor has offered Eric a sizeable discount on all hardware if his order total for the project is more than $125,000. Right now, Eric is likely to spend $118,000 with vendor. If Eric spends $7,000 his cost savings for the project will be $12,500, but he cannot purchase hardware if he cannot implement the hardware immediately due to organizational policies. Eric consults with Amy and Allen, other project managers in the organization, and asks if she needs any hardware for their projects. Both Amy and Allen need hardware and they agree to purchase the hardware through Eric’s relationship withthe vendor. What positive risk response has happened in this instance?

 

A.

Transference

B.

Exploiting

C.

Sharing

D.

Enhancing

 

Correct Answer: C

 

 

QUESTION 75

You work as a project manager for BlueWell Inc. You are preparing to plan risk responses for your project with your team. How m
any risk response types are available for a negative risk event in the project?

 

A.

Seven

B.

Three

C.

Four

D.

One

 

Correct Answer: C

 

 

QUESTION 76

Sam is the project manager of a construction project in south Florida. This area of the United States is prone to hurricanes during certain parts of the year. As part of the project plan Sam and the project team acknowledge the possibility of hurricanes and the damage the hurricane could have on the project’s deliverables, the schedule of the project, and the overall cost of the project. Once Sam and the project stakeholders acknowledge the risk of the hurricane they go on planning the project as if the risk is not likely to happen. What type of risk response is Sam using?

 

A.

Mitigation

B.

Avoidance

C.

Passive acceptance

D.

Active acceptance

 

Correct Answer: C

 

 

QUESTION 77

Fred is the project manager of the PKL project. He is working with his project team to complete the quantitative risk analysis process as a part of risk management planning. Fred understands that once the quantitative risk analysis process is complete, the process will need to be completed again in at least two other times in the project. When will the quantitative risk analysis process need to be repeated?

 

A.

Quantitative risk analysisprocess will be completed again after the plan risk response planning and as part of procurement.

B.

Quantitative risk analysis process will be completed again after the cost managementplanning and as a part of monitoring and controlling.

C.

Quantitativerisk analysis process will be completed again after new risks are identified and as part of monitoring and controlling.

D.

Quantitative risk analysis process will be completed again after the risk response planning and as a part of monitoring and controlling.

 

Correct Answer: D

 

 

QUESTION 78

You are the project manager for a construction project. The project includes a work that involves very high financial risks. You decide to insure processes so that any ill happening can be compensated. Which type of strategieshave you used to deal with the risks involved with that particular work?

 

A.

Transfer

B.

Mitigate

C.

Accept

D.

Avoid

 

Correct Answer: A

 

 

QUESTION 79

Which of the following are included in Administrative Controls? Each correct answer represents a complete solution. Choose all that apply.

 

A.

Conducting security-awareness training

B.

Screening of personnel

C.

Monitoring for intrusion

D.

Implementing change control procedures

E.

Developing policy

 

Correct Answer: ABDE

 

 

QUESTION 80

The Phase 2 of DITSCAP C&A is known as Verification. The goal of this phase is to obtain a fully integrated system for certification testing and accreditation. What are the process activities of this phase? Each correct answer represents a complete solution. Choose all that apply.

 

A.

Configuring refinement of the SSAA

B.

Assessment of the Analysis Results

C.

System development

D.

Certification analysisE. Registration

 

Correct Answer: ABCD

100% Free Download!
—Download Free Demo:CAP Demo PDF
100% Pass Guaranteed!
Download 2017 Ensurepass CAP Full Exam PDF and VCE Q&As:395
—Get 10% off your purchase! Copy it:TJDN-947R-9CCD [2017.07.01-2017.07.31]

Ensurepass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF + VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 Ensurepass IT Certification PDF and VCE